1. Find the net volume
Length × width × depth. Depth entered in millimetres is converted to metres before the cubic-metre calculation.
CONSTRUCTION
Calculate concrete volume in cubic metres for slabs, footings and rectangular pours, with a practical allowance for ready-mix ordering.
Length × width × depth. Depth entered in millimetres is converted to metres before the cubic-metre calculation.
The selected percentage is added after the net volume is calculated, so the ordering quantity stays transparent.
The final result is shown in m³, the usual basis for ready-mix concrete orders. Confirm minimum loads and delivery constraints with your supplier.
UK CONCRETE CALCULATOR GUIDE
For a rectangular pour, concrete volume is simply the plan area multiplied by the concrete depth. Use metres for length and width; this calculator accepts the depth in millimetres and converts it automatically. The net volume is shown separately from the extra allowance so you can see exactly what is being added before ordering.
| Example | Dimensions | Net concrete | With 5% allowance |
|---|---|---|---|
| Concrete slab | 5 m × 3 m × 150 mm | 2.25 m³ | 2.36 m³ |
| Strip footing | 10 m × 0.6 m × 300 mm | 1.80 m³ | 1.89 m³ |
| Concrete pad | 2 m × 2 m × 300 mm | 1.20 m³ | 1.26 m³ |
For irregular areas, divide the pour into simple rectangular sections, calculate each net volume, add them together, then apply a suitable allowance to the combined total. Site levels, excavation tolerance, formwork and sub-base conditions can all affect the actual quantity required.
The calculator's Concrete to order figure is the net volume plus your chosen allowance. It is a planning quantity rather than a supplier instruction: ready-mix suppliers can have their own minimum-load, part-load and delivery rules, and the final order should always be checked against measured site conditions immediately before the pour.
Divide millimetres by 1,000. For example, 150 mm is 0.15 m and 300 mm is 0.30 m.
The calculator starts at 5%, but the right allowance depends on the pour, ground and formwork tolerances, access and site conditions. Change it to match the job rather than treating 5% as a fixed rule.
Yes for rectangular pours: the result gives the total cubic metres after your chosen allowance, which can be used as a starting point when discussing a ready-mix order.
Split it into rectangles, calculate each section, add the net volumes together and then apply the allowance to the combined quantity.